Sanitary Sewer Lift Station Improvements - Phase 5 (CIP 455-626) March 2020 Update
March 2020 Update
Due to some schedule setbacks, the most significant of which has been with coordination with PG&E to provide permanent power to the relocated lift station the project has experienced some delays. A typical turnaround time by PG&E to energize a meter is approximately 4 weeks. Due to the fires in the north this fall, PG&E was forced to reallocate their resources to address emergency work. This resulted in a 4 month delay. In addition, other recent unforeseen conditions including various utility conflicts associated with the relocation of the last manhole and a water main break on Bounty on February 27, have contributed to delay project completion.
The anticipated substantial completion date for the work has been moved to the end of March. We apologize for the inconvenience and appreciate your patience as we complete these necessary infrastructure improvements to the sanitary sewer system.