Street Rehabilitation and Park Pathway Restoration (CIP 301-716)

Project Status: 
Approved
Project Type: 
Capital Project
Last Updated:
07/16/2024 - 11:03am
716 overview

Description

CIP 301-716 consists of street rehabilitation and pavement maintenance on Edgewater Blvd. and E. 3rd Ave and paver and bituminous layer repair at the E. Hillsdale Blvd and Center Park Ln intersection. The rehabilitation project will help to increase and maintain the City’s overall Pavement Condition Index (PCI). The PCI is a numerical index used to indicate the general condition of a pavement. BKF Engineers has prepared construction documents for the street rehabilitation and park pathway restoration and the construction agreement has been awarded to G. Bortolotto and Company. Work is expected to begin in mid-August of 2024.

Proposed Timeline:

Award Construction Contract: July 15, 2024

Construction: August 2024-November 2024

Current Status:

Construction contract awarded.

Contact Information

Public Works Department

Engineering Division
610 Foster City Boulevard
Foster City, CA  94404
Phone: (650) 286-3270
Fax: (650) 345-4626
Email: publicworks@fostercity.org
Monday - Friday, 8 am - 5 pm

Maintenance Division
100 Lincoln Centre Drive
Foster City, CA  94404
Phone: (650) 286-8140
Fax: (650) 349-7204
Email: publicworks@fostercity.org
Monday - Thursday, 8 am - 4:30 pm
Friday, 8 am - 3:30 pm​
(By appointment only)