Edgewater Park Softball and Soccer Synthetic Resurfacing

Project Status: 
In Progress
Project Type: 
Capital Project
Last Updated:
07/16/2024 - 11:25am
edgewater aerial

Description

The project includes removal of the existing synthetic turf playing surface and installation of a new synthetic turf playing surface as called out in the contract documents. Work shall also include minor base fine tuning and infill installation as called out in the documents. Construction Work shall be completed within 40 Calendar Days from the date when Contract Time commences to run, which is anticipated to start on July 15, 2024.

Proposed Timeline:

Award Construction Contract: May 20, 2024

Construction: July 2024-September 2024

Current Status:

Construction is in progress as of July 15, 2024.

Contact Information

Public Works Department

Engineering Division
610 Foster City Boulevard
Foster City, CA  94404
Phone: (650) 286-3270
Fax: (650) 345-4626
Email: publicworks@fostercity.org
Monday - Friday, 8 am - 5 pm

Maintenance Division
100 Lincoln Centre Drive
Foster City, CA  94404
Phone: (650) 286-8140
Fax: (650) 349-7204
Email: publicworks@fostercity.org
Monday - Thursday, 8 am - 4:30 pm
Friday, 8 am - 3:30 pm​
(By appointment only)